Mahendranagar, Aug 29 : The mega infrastructural and development projects which are being implemented in Kanchanpur have witnessed snail-paced progress.
The Mahakali corridor road
construction project, which was designed and executed for trade expansion up to
Tinker, the tri-country border entry point of Nepal, India, and China, has seen
dismal progress.
Only 30 km of the road section has
been blacktopped as 12 years have already elapsed since the road construction
was initiated in 2066 BS.
Though the contract was awarded
first for road construction in the Bramhadev area of Kanchanpur, it has not been
initiated due to the prolonging tree felling process.
There have been protracted hassles
in cutting down trees along the 413-km road under the project that aims to
expand access to roads from Bramhadev of Kanchanpur to Tinker of Darchula
through Dadeldhura and Baitadi.
Engineer at Mahakali Corridor
Darchula Tinker Road Project, Milan Ghatani said track opening was underway in
different sections of the corridor road.
A contract amounting to Rs 55
million was signed last year for the opening of a 15-km track from Bramhadev of
Kanchanpur to the Jogbudha area of northern Dadeldhura. It has yet to be initiated.
The Diwa-Shanidev JV was awarded the contract for the task.
Proprietor of Diwa Shanidev JV Devi
Dutta Bhatta complained that he could not advance the project works for the
past one year since the project had not obtained permission for
tree-felling.
"Had there been the permission
for tree felling, much would have been progressed so far along the
corridor", he said, adding there was no option but to wait for
permission.
As many as 1,951 trees have to be
cut down in the Kanchanpur area under the corridor. The 15-km track has to be
completed by 2080 BS.
Likewise, the construction of a postal road in Kanchanpur which had to be completed in 30 months was still
incomplete despite spending double time than the originally planned.
Similarly, contractual
responsibility was entrusted for the construction of a 62-km road from Doke
Bazaar to Daiji through Betauri in Falgun 2073 BS. As of now, only 34 km of the
road has been blacktopped, shared Information Officer of the Postal Highway
Project office Dhangadhi Padma Bahadur Madai. He further informed 28-km stretch
of the road is yet to be blacktopped.
Though the contractor was warned of
action for delay in construction works, the timeline was expanded for the fifth
time.
"Timeline has been extended up
to Mangsir (November-December) for the package from Doke Bazaar to Belauri and
next year Asar (June-July) for the remaining two packages, he said.
Likewise, the progress of the third
phase of the Mahakali Irrigation Project – which is the national priority project
being implemented in Kanchanpur has also seen snail pace.
Two other big projects of the
district – the establishment of Daiji Chhela Industrial Area and Dodhara-Chadani
dry port are also not in priority. In the current fiscal year, the government
had allocated Rs 1 billion each for both the projects but it was not gaining
momentum as anticipated.