Bhadrapur (Jhapa), Aug 13: The area
irrigated by the groundwater irrigation project has increased in the
district.
The irrigation facility from
groundwater was expanded to 1,200 more hectares in the fiscal year,
2080/81.
Information officer at project,
Ishwor Thapa, shared that financial progress of Rs 104 million was 100 percent,
while physical progress 134.17 percent. The works under the project were
carried out more than expectation, thereby resulting into maximum physical
progress in the last fiscal year.
Under the project, 15 deep tube
wells and 17 structures were constructed to expand the irrigation in the area
that had no access to canal irrigation.
However, the budget crunch was
hindering the target of reaching groundwater irrigation in 7,000 hectares of
land in five years. (RSS)